December 2017

Work Continues

Installations continue on the north end of town, hooking up roughly 20-25 homes per week. Businesses also located on the north end of town have also been hooked up. We will continue moving towards the heart of the city as progress continues installing services to our customers.
[+] Read More
October 2017

Installation Begins

This week marks the beginning of the installation process for the Rushford fiber build. Installs will begin on the north side of town.
[+] Read More
September 2017

Progress

Splicing on the Lanesboro fiber project is about 60% complete. Installation is set to begin in early October.
[+] Read More
August 2017

Splicing Continues

Splicing is about 40% complete and equipment is being installed at AcenTek's headend and central office. Based on the progress so far, we hope to be able to start connecting customers on the north side of the city in mid-September.
[+] Read More
July 2017
Construction Phase Complete

Construction Phase Complete

The construction phase of the fiber build in Rushford is now complete.  The next step in the process is splicing, which will continue through the end of the year. The overall fiber project looks to be on track for a completion date of March 2018.
[+] Read More
Progress Continues...

Progress Continues...

South Rushford is about 98% complete, as far as mainline drilling goes, with only 40 drops left to complete. The Brooklyn Park area is complete (for mainline drilling) with only 20 drops left.  
[+] Read More
June 2017
Construction Half Done

Construction Half Done

We are excited to report that the construction phase is roughly 50% complete in Rushford. We've buried over 12,000 feet of fiber optic cable so far. We are finishing up on the east side of town (Brooklyn Park) and will be moving to the south west side of town next.
[+] Read More
May 2017
Moving South

Moving South

Construction is finishing up on the north end of town in the next day or two. Our crews have now begun work in the area south and west of Rush Creek. We have fiber up to the new school; splicers are now working there. 
[+] Read More
Construction Begins in Rushford

Construction Begins in Rushford

Construction began in the city of Rushford. You may have noticed many trucks in town with cable spools and other large equipment used for boring the fiber in the ground. This phase of the process is a joint effort so you may see some workers and vehicles that are not labeled AcenTek. We are working beside Central Cable, contractors out of Waupun, WI. We will be beginning on the north end of town and are moving south.
[+] Read More

THE PLAN:

- 917 homes and businesses will be addressed with this fiber build

- Construction will take place throughout the summer of 2017
- Most of May will be spent on the north end of town
- June will be spent working near the middle of the town, those locations fed by the central office
- Work in July will include the area south of the school, east of Rush Creek
- August will be spent working on South Rushford Village

- Splicing will follow construction and will continue through the end of the year